Bridge demolition on the highway D10

During the reconstruction of the highway D10 our company demolished an old bridge, which was in very bad shape, near the Brodce township.
Highway was closed in both directions for a short period – road closure began on Saturday 25. 6. 2016 at 14.00 and traffic was restored in the following morning 26. 6. 2016 at 8.00.

We used a wide range of machinery from demolition excavators, loaders and dump trucks to cleaning technology for final cleaning of the road.

The actual demolition of the bridge lasted 6 hours and a finished work, including all the cleaning works, was handed over against the plan with a large slack.