Completion of the installation of the footbridge in Česká Třebová

We have completed the installation of the footbridge over the railway yard in Česká Třebová. Using a Liebherr LTR 1100 crawler crane, we installed the last section of the footbridge, 27 meters long and weighing 24 tons. The total length of the footbridge is 108 meters. We installed the previous two sections with our Liebherr LTM 1650-8.1 wheeled crane.